SIN119

Project Outline:

S&T Cover worked in conjunction with Network Rail to make significant improvements to the Internal and external Earthing arrangements on 207 location cases within the Wessex route.

SIN119 inspections, desk top studies and surveys were completed to understand the scale of the defects within Location Cases. This allowed S&T Cover to implement the required Design, which resulted in the following equipment being Installed and Tested to resolve the Earthing touch potential issues:

  • Earthing (Rod and Matt)
  • Bonding
  • Shrouding
PROJECT SUMMARY:

Asset Condition Surveys

Design

Location Case Installation

Earthing Installation

G110 Testing